Accounting Software Project - March 2002

This table shows the load of each day for all the tasks. Additionally the resources used for each task are listed. Since the project start was delayed, the delayed schedule differs significantly from the original plan.

No. Name Start End Scenario Jan 2002 Feb 2002 Mar 2002 Apr 2002
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31  1  2  3  4  5  6  7  8  9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28  1  2  3  4  5  6  7  8  9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31  1  2  3  4  5  6  7  8  9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
1. Accounting Software 2002-01-16 2002-04-16 Plan v=3.5 3.5 3.5 == == 3.5 3.5 3.5 3.5 3.5 == == 4 4 4 4 3 == == 3 4 4 4 4 == == 4 4 4 4 4 == == 4 4 4 4 4 == == 4 4 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 1.8 1.8 == == 1.8 1.8 1.8 1.8 1.8 == == 1.8 1.8 1.8 1.8 1.8 == == 1.8 1.3=v        
2002-01-20 2002-04-24 Delayed     v= 3.5 3.5 3.5 3.5 3.5 == == 3.5 3.5 3.5 4 3 == == 3 4 4 4 4 == == 4 4 4 4 4 == == 4 4 4 4 4 == == 4 4 4 4 4 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 2 2 == == 2 2 2 1.8 1.8 == == 1.8 1.8 1.8 1.8 1.8 == == 1.8 1.8 1.8 1.8 1.8 == == 1.8 1.8 0.5=v    
2. Milestones 2002-01-16 2002-04-16 Plan v= == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == =v        
2002-01-20 2002-04-24 Delayed     v= == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == == =v    
3. Projectstart 2002-01-16 2002-01-16 Plan <>                                                                
2002-01-20 2002-01-20 Delayed     <>                                                            
4. Technology Preview 2002-03-01 2002-03-01 Plan                           <>                                      
2002-03-06 2002-03-06 Delayed                                 <>                                
5. Betaversion 2002-04-01 2002-04-01 Plan                                                 <>                
2002-04-08 2002-04-08 Delayed                                                     <>            
6. Ship Product to customer 2002-04-16 2002-04-16 Plan                                                           <>        
2002-04-24 2002-04-24 Delayed                                                               <>    
7. Specification 2002-01-16 2002-01-25 Plan [=2.5 2.5 2.5 == == 2.5 2.5 2.5 2.5 2.5=]                                                          
2002-01-21 2002-01-30 Delayed     [=2.5 2.5 2.5 2.5 2.5 == == 2.5 2.5 2.5=]                                                        
  Developers     Plan 2.5 2.5 2.5   2.5 2.5 2.5 2.5 2.5                                                          
Delayed     2.5 2.5 2.5 2.5 2.5   2.5 2.5 2.5                                                        
  Paul Smith     Plan 1 1 1   1 1 1 1 1