project "Scrum Example Project" 2012-02-01 +4m { now 2012-03-07 } resource r1 "R1" resource r2 "R2" resource r3 "R3" # This example uses a very simple WBS that groups tasks by sprint. For # larger projects, a classical WBS that breaks tasks into smaller # tasks and so on is probably more appropriate. The reports can then # select the sprint context by date. task product "Product" { task s1 "Sprint 1" { task t1 "T1" { effort 5d allocate r1 } task t2 "T2" { effort 3d allocate r1 depends !t1 } task t3 "T3" { effort 7d allocate r1 } task t4 "T4" { effort 4d allocate r2 depends !t2 } } task s2 "Sprint 2" { depends !s1 task t1 "T1" { effort 3d allocate r2 } task t2 "T2" { effort 4d allocate r3 depends !t1 } task t3 "T3" { effort 6d allocate r1 } task t4 "T4" { effort 5d allocate r3 depends !t3 } task t5 "T5" { effort 3d allocate r2 depends !t1 } } task s3 "Sprint 3" { depends !s2 task t1 "T1" { effort 6d allocate r1 depends product.s1.t2 } task t2 "T2" { effort 4d allocate r3 depends !t1 } task t3 "T3" { effort 4d allocate r1 depends product.s2.t4 } task t4 "T4" { effort 7d allocate r2 depends !t3 } task t5 "T5" { effort 5d allocate r2 depends !t1 } } } navigator menu textreport "" { header -8<- == Scrum Example Project == <[navigator id='menu']> ->8- formats html textreport "" { columns name, status, effort, resources taskreport "Product Backlog" { } taskreport "Sprint 1 Backlog" { taskroot product.s1 } taskreport "Sprint 2 Backlog" { taskroot product.s2 } taskreport "Sprint 3 Backlog" { taskroot product.s3 } title "Backlogs" purge formats } textreport "" { sorttasks id.up width 800 tracereport "Product Burndown" { columns opentasks hidetask plan.id != "product" } tracereport "Sprint 1 Burndown" { columns opentasks hidetask plan.id != "product.s1" } tracereport "Sprint 2 Burndown" { columns opentasks hidetask plan.id != "product.s2" } tracereport "Sprint 3 Burndown" { columns opentasks hidetask plan.id != "product.s3" } title "Burndown Charts" purge formats } purge formats }